A properly constructed scaffold offers the best
possible work environment for people working
at heights. People erecting scaffold must be
appropriately trained and supervised. Australian Scaffold Sales therefore recommends that all
scaffolds are erected by persons holding a
certificate of competency, however:
- For scaffolds with a working platform height of
4 metres or less, any physically sound person
may erect a scaffold.
- For scaffolds where a person or object can fall
more than 4 metres the person erecting the
scaffold must have a certificate of competency.
- As some scaffold components are quite heavy
the physical capabilities of persons (erectors)
erecting the equipment should always be taken
into consideration.
- A minimum number of 2 people are required to
erect a scaffold safely up to a height of 6 metres.
Above 6 metres a crew size of 3 is recommended.
|